The Details
Challenge
Develop land for use by Lowe’s Canada for new expansion store.
Solution
The solution involved the cutting/filling of 15,000 m3 with export of 10,000 m3 for a total of 25,000 m3. Included in this project was the installation of 1500 meters of deep underground storm sewer, water main and sanitary sewers. [/vc_column_text][/vc_column][/vc_row]